Week of September 28, 2015 | KC Downtown Streetcar Progress Update

CROSSROADS
  • 20th - Truman Rd: Road resurfacing continues on the outside lanes of Main Street. No street parking on Main Street from Truman Road south to 20th Street
  • Pershing: Drainage work continues. Construction of "Union Station" stop begins 
  • 19th: Conduit installation 
CENTRAL BUSINESS DISTRICT
  • 9th: Northbound "Library stop" platform construction continues. 
  • 11th & Petticoat: Traffic signal work continues. Petticoat open to local access only from Walnut. Petticoat closed at Main Street
RIVER MARKET
  • 3rd & Grand: Construction on "River Market North" stop starts Wednesday. Delaware - Grand open to eastbound traffic only. Walnut, 3rd to 2nd, northbound traffic only
  • 5th: Crosswalk construction. Open to westbound traffic only from Grand to Main. Open to two-way traffic from Main to Delaware.

 

Streetcar platform construction is ongoing. Anticipated completion of all private (third-party) utility work is Summer 2015. KC Streetcar Constructors' track work continues in the Central Business District through July 2015.  Systems work, such as the overhead power system, will continue through Summer 2015. Streetcar vehicles estimated to arrive in fall 2015. Systems testing estimated to begin in mid fall 2015.
About the Downtown Kansas City Streetcar Starter Line
The two-mile, north-south Downtown KC Streetcar will travel along Main Street and connect the River Market to Crown Center and Union Station, serving the Central Business District, the Crossroads Art District, and the Power and Light District, as well as numerous businesses, restaurants, art galleries, educational facilities and residents. 

For more information visit us on the Web, Facebook and Twitter or contact the Project Hotline at 816-804-8882 or info@kcstreetcar.org.
About KC Streetcar Constructors 
KC Streetcar Constructors (KCSC) is the project team building the two-mile KC Downtown Streetcar starter line. KCSC is a joint venture of St. Joseph-based Herzog Transit Contracting Corp. and California rail builder Stacy and Witbeck, Inc.
About this Update
This weekly construction update provides weekly, at-a-glance information related to the streetcar construction that is taking place this week.  For more information, including upcoming work, check out the project website and follow the streetcar on Twitter @kcstreetcar and Facebook. All work activities and time frames are subject to change due to inclement weather or other unforeseen circumstances. 