20th to 17th
Starting Jan 10, OCS work on the east side of Main St from Truman Rd South to 18th St. Work will take place within the east side parking lane.
Northbound track work between 18th and north of 20th St anticipated for completion Jan. 23, weather dependent.
Week of Jan 12: Southbound track construction to start at 20th St. 20th St open to one lane east bound ONLY on Jan 12 from 8am-2pm. Westbound traffic from Walnut to Main is closed.
Week of Jan 12: 19th St closed to eastbound traffic between Main and Walnut due to Water Services work. THIS IS NOT STREETCAR RELATED.
|
|